KPTCL Substation – 66/11KV, Nayakanahatty
Project Capacity
5MW + 4.95MW Solar Power Plant
Project Location
Gowripura Village
Client Name
NEO GREEN POWER Pvt. Ltd. & Vahini Irrigation Pvt. Ltd.
Scope of Work:
NEO GREEN POWER Pvt. Ltd. & Vahini Irrigation Pvt. Ltd.
- Construction of Transmission Line ( ~ 6KM) - Supply & Erection
- Construction of 11KV Terminal Bay - 5MW & 4.95MW Solar Power Plant - Supply & Erection
- Construction of Switch Yard - 5MW & 4.95MW Solar Power Plant - Supply & Erection
KPTCL Substation – 66/11KV, Nayakanahatty
MR Power Solutions successfully executed critical power evacuation infrastructure for the 66/11KV KPTCL Substation at Nayakanahatty, supporting a combined 9.95 MW Solar Power Plant (5 MW + 4.95 MW).
Project Overview
The project ensured reliable grid connectivity and efficient power transmission from the solar generation site to the utility network, highlighting MR Power Solutions’ expertise in high-voltage transmission systems and substation execution.
Project Capacity
5 MW + 4.95 MW Solar Power Plant
Project Location
Gowripura Village
Client
NEO GREEN POWER Pvt. Ltd.
Vahini Irrigation Pvt. Ltd.
Substation Type
66/11 KV KPTCL Substation
Scope of Work
1. Transmission Line Construction (~6 KM)
- Design, supply, and erection of approximately 6 KM transmission line
- Installation of structures, conductors, insulators, and hardware
- Stringing, sagging, and tensioning as per KPTCL standards
- Ensured alignment, mechanical strength, and electrical clearances
- Compliance with safety and grid connectivity norms
2. 11KV Terminal Bay Construction
- Complete terminal bay construction for both solar plants
- Installation of isolators, circuit breakers, CTs, PTs & control panels
- Integration with substation and evacuation systems
- Testing, commissioning, and grid synchronization
3. Switch Yard Construction
- Design and execution of switchyard infrastructure
- Civil, structural, and electrical works
- Earthing, lightning protection, and cable routing
- End-to-end testing and energization readiness
Execution Highlights
- End-to-end EPC execution with strict KPTCL compliance
- Timely completion with focus on quality and safety
- Seamless coordination with utility authorities and clients
- Robust infrastructure for uninterrupted renewable energy flow
Project Impact
The project enabled successful evacuation of 9.95 MW of clean solar power, strengthening regional renewable energy capacity while ensuring long-term grid stability and reliable power transmission.